Overview:
Users can select work days for their companies, and create (or import) holidays.
When enabled, all calculations regarding the duration and risk of tasks will take the working days under consideration.
Note: If a task start date is on Thursday, and ends next Wednesday - the old duration will be 6 days. The new duration will be 4 days if Saturday and Sunday are selected as non-working days.
Workspace Management:
Users can control on the workspace level:
-
Workdays
-
Workspace specific holidays (they will apply to every project in the workspace)
-
Mass upload holidays via CSV import
On project level:
-
Project-specific holidays - Users can set project and client specific holidays. These holidays will be merged with the workspace holidays to create project specific days off
Effects on Dateshift:
-
Shift selected tasks - when you shift with 5 days, they will be 5 working days - so it will adjust the dates accordingly by skipping the non-working days and holidays
-
Risk - Risk is also affected, and will produce adjusted numbers
-
Duration of tasks - Duration will only take into account working days